Skip to main content

How do I install LED modules on a DVLED display?

Answer: When installing the module, first align the edges with the adjacent LED module(s) and then carefully install the module onto the cabinet. If the edges are raised, lightly tap the edges of the module with your palm to make it fit. Note: Do NOT tap the LED Modules hard. If they are not going in after being lightly tapped, refer to this...

Should DVLED installation be done with Power On or Power Off?

Answer: DVLED displays can only be powered on when the System Control Box has been installed. The LED Modules are to be installed after. However, when installing the LED Modules, it is recommended to install with the power turned on, in order to assess display issues. It's better to replace as you go, since finding an issue after many tiles...

How do I remove LED Modules from the DVLED Display?

Solution  Step 1: Wear anti-static gloves before handling the LED Modules. Step 2: Remove the Vacuum Suction Tool from the box and press its power switch to use it. Please charge it with the included power supply and make sure the vacuum suction tool is kept in a fully charged state. Step 3: Move the Vacuum Suction Tool to t...

What is the Vacuum Suction Tool used for on DVLED Displays?

Answer: The Vacuum Suction Tool is used for removing LED Modules (or LED tiles) from the DVLED Display.  See "How do I remove LED Modules from the dvLED Display?" for more information on how to use the Vacuum Suction Tool.

How many spare LED Modules are given for a DVLED Display?

Answer: According to the User Guides, the quantity of spare LED modules will vary by country. Please contact your regional ViewSonic sales office for further information.

What is the Cabinet installation order of the DVLED Wall-mount configuration?

The Cabinet installation order varies from the Floor Stand configuration. Please follow the steps in the respective order for the Wall-mount configuration: Cabinet C moved to the center of the installation position, and Cabinet B placed to the left side of Cabinet C Hex wrench used to help align and ensure no tile-to-tile steps before engagi...

What is the System Control Box installation order of DVLED Displays?

The System Control Box installation order is the same for the Wall-mount and Floor Stand configuration. Please follow the steps in the respective order for the System Control Box installation order: Seven system control box attachment points screwed down Control box Power cables: - Running from the back of the control box? - Running from ...

What is the LED Module installation order of the DVLED Displays?

The LED Module installation order is the same for the Wall-mount and Floor Stand configuration. Please follow the steps in the respective order for the LED module installation order: Anti-static gloves worn Began handling with delicacy, following numbers marked on the box of each module Confirmed arrow facing upwards when installing the LE...

How many sets of Ethernet and Power cables need to be attached to DVLED Cabinets?

Answer: The number of Ethernet and Power cable sets that need to be attached from the System Control Box to DVLED Display Cabinets will vary depending on Cabinet quantity. Please refer to this link to find the Cabinet quantity for the appropriate model. 

What do I need to do before installing the System Control Box Cover for a DVLED Display?

Answer: Before attaching the System Control Box Cover, connect the control box’s power cable to the control box cover's Power Button, and then install the cover with screws to complete the installation of the System Control Box.

Support

Contact Us

Contact Us directly if you’re unable to get the answers and solutions for your ViewSonic products.